PERT Network Analyzer (Expected Duration & Variance)

· Last updated:2026-08-26

Three-point PERT estimates: te and σ² per activity, critical path, expected project duration and variance, and normal completion probability for a target time.

Execution

Run this tool

Fill in the form, run the tool, and review the result in one place.

Samples

Examples that match this tool

Related

Continue with connected tools and hubs

Written by the Elysia Tools team

Tool usage guide

Learn when to use this tool, what it supports, and how real users apply it.

Key facts

Category
Math & Numbers
Input types
textarea, number
Output type
text
Sample coverage
4
API ready
Yes

Overview

The PERT Network Analyzer performs Program Evaluation and Review Technique calculations using three-point duration estimates (optimistic, most likely, and pessimistic). It computes expected duration and variance for each activity, identifies the critical path across network dependencies, calculates total project expected duration and variance, and determines the probability of meeting an optional target completion deadline.

When to use

  • Evaluating project schedule risk when task durations involve uncertainty and require three-point estimations.
  • Identifying the critical path and total expected project duration from a set of dependent activities.
  • Calculating the statistical probability (Z-score) of completing a project by a specific target deadline.

How it works

  1. 1Enter activity details line-by-line with name, optimistic time (a), most likely time (m), pessimistic time (b), and predecessor names.
  2. 2The tool calculates the expected duration te = (a + 4m + b) / 6 and variance σ² = ((b - a) / 6)² for each activity.
  3. 3The network resolves dependencies to find the critical path, total expected duration (TE), and total critical path variance.
  4. 4If an optional target time (T) is provided, the tool calculates Z = (T - TE) / σ and outputs the normal completion probability.

Use cases

  • Project managers assessing schedule confidence intervals for complex multi-phase initiatives.
  • Operations research analysts modeling project network dependencies and activity float.
  • Engineering leads presenting statistical delivery timelines and contingency buffers to stakeholders.

Examples

1. Four-Activity Branching Network

Project Manager

Background

Managing a project with parallel development paths where one branch has high uncertainty.

Problem

Determine which path is critical and evaluate the likelihood of meeting a 16-day schedule deadline.

How to use

Input activities A, B, C, and D with their three-point estimates and predecessor relationships, setting a target completion time of 16.

Activities:
A, 2, 4, 6, -
B, 3, 5, 7, A
C, 2, 3, 10, A
D, 4, 6, 8, B C
Target Time: 16
Decimal Places: 4

Outcome

Identifies the critical path A → B → D with expected duration TE = 15, project variance σ² = 1.3333, and an 80.7% probability of completion by day 16.

2. Serial Chain Milestone Analysis

Operations Analyst

Background

Evaluating a strict sequential process containing three successive execution phases.

Problem

Compute the cumulative expected timeline and variance across the full sequential chain to verify an 18-day target.

How to use

Enter the serial tasks in sequence where each task depends directly on the previous one, and set the target completion time to 18.

FAQ

What format is required for the activity input list?

Enter one activity per line formatted as: name, optimistic (a), most likely (m), pessimistic (b), followed by predecessor names separated by spaces, or '-' if there are no predecessors.

How are expected duration and variance calculated for each activity?

Expected duration uses the standard PERT formula te = (a + 4m + b) / 6, and variance is computed as σ² = ((b - a) / 6)².

How is the total project variance calculated?

Total project variance is calculated by summing the variances (σ²) of only the activities located on the critical path.

What happens if an activity violates the a ≤ m ≤ b rule?

The analyzer validates that the optimistic duration does not exceed the most likely duration, and the most likely does not exceed the pessimistic duration, rejecting invalid entries.

What does the completion probability represent?

Using the standard normal cumulative distribution Φ(Z), it calculates the statistical probability of finishing the project within your specified target time T.

Home
Tools3212
Samples593
Visualizations471
Viewers103
Hubs239
Tags333
Images, Audio & Video657

Image, audio, and video processing, conversion, and optimization tools

Math, Date & Finance647

Calculators, numerics, date logic, statistics, and finance tools

Design & Color298

Color, layout, graphics, visual styling, and design helper tools

Text & Writing209

Writing, cleanup, formatting, extraction, and text analysis tools

Developer & Web193

Developer utilities, networking, web debugging, and automation helpers

Conversion & Encoding175

Format, file, archive, unit, and encoding conversion tools

Lead Generation Quiz Launch and Contact Handoff
Memorial Drafts: Family Review and Print Handoff
Private Habit Records: Backup, Restore and Sharing Review
Article to X and LinkedIn Drafts: Fact Review and Handoff
Markdown Interactive Deck Review and Offline Handoff

© 2026 Elysia Tools. All rights reserved.

DocsPricingAboutTerms of ServicePrivacy PolicyCookiesContact
File System

Path Analyzer Samples

Comprehensive collection of file system paths from Windows, Linux, and macOS for path analysis and testing

Python

Web Image Processing Python Samples

Web Python image processing examples using PIL/Pillow including reading, saving, resizing, and format conversion

Web Standards

ActivityPub Decentralized Social Network

ActivityPub protocol examples for federated social networks, Mastodon compatibility, and decentralized social media

Security

Network Security and SSL/TLS Configuration

Comprehensive network security examples including SSL/TLS configuration, firewall rules, VPN setup, and network scanning protection

Math & Numbers

Perfect Number Checker

σ(n) = 2n ⟺ perfect. Factorization-based σ(n), proper-divisor sum, deficient/perfect/abundant classification, abundancy index, Euclid–Euler form. n ≤ 10¹².

Math & Numbers

Dimensional Analysis Unit Cancellation Tutor

Step-by-step factor-label unit cancellation with inverted-factor diagnosis and optional student-answer checking.

Math & Numbers

Three-Phase Short-Circuit Current Calculator (IEC 60909)

Estimate the three-phase symmetric short-circuit current using the IEC 60909 far-from-generator method: I"_k = c·U_n/(√3·|Z|) and i_p = κ·√2·I"_k with κ = 1.02 + 0.98·e^(−3R/X). Source impedance is the series sum of transformer and line R/X.

Math & Numbers

Transformer Impedance Transfer Calculator

Reflect an impedance through an ideal transformer: Z' = a²·Z, where a = N₁/N₂. Supports secondary→primary and primary→secondary directions; a can be given directly or derived from N₁/N₂. Also returns admittance Y and reflected admittance.

Activities:
A, 1, 3, 5, -
B, 3, 6, 9, A
C, 2, 4, 12, B
Target Time: 18
Decimal Places: 4

Outcome

Finds critical path A → B → C with total expected duration TE = 14, variance σ² = 4.2222, and a 97.4% probability of finishing within 18 days.